Proposed Implementation Schedule

According to our project guidelines, we plan on developing and producing a final product in 10 weeks. Table 1 below is an outline of our preliminary per week breakdown of what we hope to accomplish.

Table 1: Preliminary weekly goals
Week Goal
April 8 - 14
  • Obtain all necessary parts
  • Determine the necessary algorithms for finding angles and coordinates
  • Explore the tradeoffs between tables and floating-point emulations
  • Explore Windows CE programming paradigm and get a sample application that demonstrates and understanding of the programming environment
  • Explore the camera interfaces
  • Begin work on preliminary design package
April 15 - 21
  • Explorer RF and IR tradeoffs
  • Begin synthesizing image processing algorithms into hardware
  • Begin development of Windows CE application used to display information to the user
  • Submit preliminary design package
  • Prepare for preliminary design package presentation
April 22 - 28
  • Debug the image capture and image processing subsystems
  • Determine the wireless protocol that sits on top of RF or IR which will be used to transmit the data to the Windows CE device
  • Debug the Windows CE application
  • Submit revised preliminary design package
April 29 - May 5
  • Begin data correlation subsystem
  • Begin work on final design package
May 6 - 12
  • Debug data correlation subsystem
  • Integrate the data correlation subsystem with image capture and image processing subsystem
  • Develop the RF or IR communication link in hardware
  • Submit final design package
  • Prepare for final design presentation
May 13 - 19
  • Debug the RF and IR communication link
  • Integrate all subsystems together and test the entire system
  • Submit revised final design package
May 20 - 26
  • Begin product brochure
  • Plan a demonstration
  • Finalize all design constraints, specifications, and assumptions we made
  • Begin final project report
May 27 - June 2
  • Finish project brochure
  • Finish final project report