Schedule:

 

Time

Task

Progress

Week 1
  • Design decisions  

Done

Week 2
  • Write a proposal, order parts and get familiar with tools available in the lab

Done

Week 3
  • Determine the operation of Etank’s remote control unit
  • Buying the switch and connect to the unit

Done

  • Interface to the XSV-300 board:
    • Understanding how the parallel communication with XSV-300 works
    • Write a protocol to control the switches using XSV-300
  • Understand how RF works 

Done

Week 4
  • Understand how Compass works
  • Understand how Sonar works
  • Decide to use a Micro-controller, XS-40 or PIC processor to communicate with the Tank 
  • Write the Preliminary Design Package

Done

Week 5
  • Write a protocol to control the RF using XSV-300
  • Implement the serial communication port of XSV-300
  • Write a protocol to control the Compass using the PIC Micro-controller
  • Write a protocol to control the Sonar using the PIC Micro-controller
  • Write a protocol to control the RF using the PIC Micro-controller
  • Revise the Preliminary Design Package

Done

Week 6
  • Start coding the user interface program.
  • Review other's design

Done

Week 7
  • Figure out how to slow down the tank and measure its speed
  • Look into adding the pen to the tank
  • Write the Final Design Package

Done

Week 8
  • Interface the PIC processor and XSV-300 board to the RF unit on Etank
  • Finish coding the user interface program
  • Finalize debugging and integration
  • Revise the Final Design Package

Done

Week 9
  • Finalize debugging and integration
  • Review other's design  

Done

Week 10
  • Finalize debugging
  • Project demo

Done

Week 11
  • Project Brochure 
  • Project Report
  • Graduation Party! Dating, Dancing, and Drinking!!!