1. Story Reel
a.
separate
shots. Develop primitives for characters and props.
Divide shots up among group. Divide deadlines in thirds.
2. Concept Art
a.
Elevator
is presented April 10th. All interiors and Characters by April 10th
3. Animatics/ Layout
a.
Thursday
April 5 -- Storyreel review and final. Shot assignments. Start one third of the
animatics shots
b.
April 10th -- 10 shots for animatics
c.
April
12 -- last 10 shots – animatics
d.
Review
and revise. Revisions done by April 15. Layout takes final props
e.
April
24th. Layout complete by April 30th.
4. Prop and Character Modeling
a.
Five
main characters -- Assigned April 10th. Due for first review -- April 17th.
Turntables. Final character models due April 19.
b.
Elevator
operator, couple, girl, operator #2 Props Inside Elevator, Elevator Interior --
Seat, walls, gate, buttons, Doors, Photo on door, floor, Assign characters and
props April 10th. Due for review --
April 19th.
c.
Outside
the Elevator. Boat, buoy, exterior
environments TBD. Assigned April 12th
Due for first review April 20th.
5. Character Rigging.
a.
5
Characters -- rigging and lip sync. April 19th to Rigging. Rigging -- First
review April 26th. Revise rigging. Final characters to motion April 28th.
6. Motion
a.
Shots
assigned April 12th. Investigate acting and characters. Test Rigging. Learn lipsync.
b.
Shot
1 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
c.
Shot
2 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
d.
Shot
3 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
e.
Shot
4 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
f.
Shot
5 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
g.
Shot
6 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
h.
Shot
7 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
i.
Shot
8 Review May 8, Second review 10, Third review 12th. Finalled 5/16th
j.
Shot
9 Review May 8, Second review 10th, Final Review 5/18th
k.
Shot
10 Review May 12, Second review 16th, Final Review 5/20th
l.
Shot
11 Review May 12, Second review 16th, Final Review 5/20th
m.
Shot
12 Review May 12, Second review 16th, Final Review 5/20th
n.
Shot
13 Review May 12, Second review 16th, Final Review 5/20th
o.
Shot
14 Review May 12, Second review 16th, Final Review 5/20th
p.
Shot
15 Review May 12, Second review 16th, Final Review 5/20th
q.
Shot
16 Review May 12, Second review 16th, Final Review 5/20th
r.
Shot
17 Review May 12, Second review 16th, Final Review 5/20th
s.
Shot
18 Review May 16, Second review 20th, Final Review 5/24th
t.
Shot
19 Review May 16, Second review 20th, Final Review 5/24th
u.
Shot
20 Review May 16, Second review 20th, Final Review 5/24th
7. Shading/ Painters --
a.
Props
and character models go to shaders by April 24th.
b.
First
Shader review -- April 27th. Second review due May 1.
8. Lighting
a.
Lighting
swatches started April 5th. Complete by April 12th.
b.
Animated
lighting tests for storyreel -- April 25th.
c.
Set
i.
Shaded
props due to lighting April 30th. Lighting due for set May 14th.
d.
Character
i.
Shot
1 Review May 16th, Second review 18th, Final Review May 19th
ii.
Shot
2 Review May 11, Second review 14th, Final Review May 19th
iii.
Shot
3 Review May 11, Second review 14th, Final Review May 19th
iv.
Shot
4 Review May 11, Second review 14th, Final Review May 19th
v.
Shot
5 Review May 11, Second review 14th, Final Review May 19th
vi.
Shot
6 Review May 11, Second review 14th, Final Review May 19th
vii.
Shot
7 Review May 11, Second review 14th, Final Review May 19th
viii.
Shot
8 Review May 11, Second review 14th, Final Review May 19th
ix.
Shot
9 Review May 16, Second review 19th, Final Review 5/24th
x.
Shot
10 Review May 16, Second review 19th, Final Review 5/24th
xi.
Shot
11 Review May 16, Second review 19th, Final Review 5/24th
xii.
Shot
12 Review May 16, Second review 19th, Final Review 5/24th
xiii.
Shot
13 Review May 16, Second review 19th, Final Review 5/24th
xiv.
Shot
14 Review May 16, Second review 19th, Final Review 5/24th
xv.
Shot
15 Review May 16, Second review 19th, Final Review 5/24th
xvi.
Shot
16 Review May 16, Second review 19th, Final Review 5/24th
xvii.
Shot
17 Review May 19, Second review 24th, Final Review 5/28th
xviii.
Shot
18 Review May 19, Second review 24th, Final Review 5/28th
xix.
Shot
19 Review May 19, Second review 24th, Final Review 5/28th
xx.
Shot
20 Review May 19, Second review 24th, Final Review 5/28th
9. Rendering
a.
Shots
1-8 Recieved by render team May 19th
b.
Shots
9-16 Received by render group May 24th
c.
Shots
17- 20 Received by render group May 28th
10.EFX
a.
April
29th -- start on shots 1-8 -- Finalled on May 19th
b.
Shots
9 - 16 -- Finalled by May 24th
c.
Shots
17 –20 -- Finalled by May 28th
11.Post
Production
a.
Shots
and compositing.
b.
Color
correction May 26th for review. Finalled by June 2nd.
12.Poster
a.
May
19th. Finalled lit shots from sets to Poster.
b.
Poster
design review May 25th. Off to printer May 28th.
c.
PROGRAM
DESIGN May 19th -- first review. Off to printer May 19th.
13.Credits
a.
Review
May 28th. Finalled June 1.
b.
outtakes
-- June 4th.