Teams Update
Monday, August 5, 2002

The SegFaults

Team Status

Team Plan:

Mikam Tribe

Team Status

Team Plan

  1. We will still be working with the cab console, scheduler, and datastore to get use case 2 working. I don't know how much longer that will take. If we can get things to run smoothly, we should be done by the end of Monday 8/5.
  2. After we complete use case 2, we will begin on the system bootup and installation. We plan to get this done by Wednesday 8/7. The team leads will meet 8/5 to discuss how this will be done.
  3. If we can get system bootup and installation done by 8/7, we then need to implement at least the 4th use case where the cab drops off the customer. This should be easy for the Model since most of the code is already written.

Team Doug

Team Status

Team Plan

The Masters

Team Status:

Team Plan:

Team Tsunami

Team Status

Team Plan