In this homework, you will implement Kruskal's algorithm to generate mazes and Dijkstra's algorithm to solve them.
You will use these files from prior assignments:
src/main/java/datastructures/concrete/DoubleLinkedList.java
src/main/java/datastructures/concrete/dictionaries/ArrayDictionary.java
src/main/java/datastructures/concrete/dictionaries/ChainedHashDictionary.java
src/main/java/datastructures/concrete/ChainedHashSet.java
src/main/java/datastructures/concrete/ArrayHeap.java
src/main/java/misc/Sorter.java
If you have chosen a new partner for this assignment, choose either of your submissions from and verify that these are functioning properly.
You will be modifying the following files:
src/main/java/datastructures/concrete/ArrayDisjointSet.java
src/main/java/datastructures/concrete/Graph.java
src/main/java/mazes/generators/maze/KruskalMazeCarver.java
Additionally, here are a few more files that you might want to review while completing the assignment (note that this is just a starting point, not necessarily an exhaustive list):
src/main/java/datastructures/interfaces/IDisjointSet.java
src/test/java/datastructures/TestArrayDisjointSet.java
src/test/java/datastructures/TestGraph.java
src/main/java/datastructures/interfaces/IEdge.java
src/main/java/mazes/entities/Wall.java
src/main/java/mazes/entities/Room.java
src/main/java/mazes/entities/Maze.java
src/main/java/mazes/Main.java
src/main/java/mazes/gui/MainWindow.java
This is a team assignment. This entire homework is due on Friday, June 7 at 11:59pm.
Here are some baseline expectations you should meet in all projects:
Follow the course collaboration policies
DO NOT use any classes from
java.util.*
. There are only two exceptions to this rule:
You may import and use the following classes:
java.util.Iterator
java.util.NoSuchElementException
java.util.Objects
java.util.Arrays
You may import and use anything from java.util.*
within your testing code.
DO NOT make modifications to instructor-provided code (unless told otherwise). If you need to temporarily change our code for debugging, make sure to change it back afterwards.
Clone the starter code from GitLab and open the project in your IDE. See the instructions from HW1 if you need a reminder on how to do this.
Copy all of your data structures, algorithms, and tests from the previous homework to this new one.
Finally, make sure everything works.
Try running TestGraph.java
and make sure the tests run.
Try running SanityCheck.java
, and try running Checkstyle.
Checkstyle should still report the same 5 errors with SanityCheck.java
as it did in the previous projects.
Task: make sure you can run Main.java
Navigate to the mazes
package and run Main.java
.
This will launch a program that will (eventually) generate and solve mazes.
The GUI consists of two main regions. The large region at the top, which will initially contain your maze, and a few options and buttons at the bottom.
Here is a brief explanation of the user interface:
The "Base maze shape" combobox controls what underlying "shape" your maze will have. The default is "Grid", which creates a maze where each room is a rectangle.
Try switching the option to "Voronoi" and click the "Generate new maze" button to the left. This will generate a maze where the rooms are more irregular.
The "Maze generator" combobox controls the actual maze generation process—it takes the initial set of room and removes edges to generate a plausible maze.
The default option is "Do not delete any edges", which, as you may have guessed, does not delete any edges.
Now, try picking one of the "Delete random edges" options and generate a new maze. You should now see some of the edges removed and see something that more closely resembles a maze.
Unfortunately, the "randomly remove edges" strategy is not that great. If we remove 30% of the edges, the maze is too easy. If we remove 50% of the edges, we often end up with an unsolvable maze. (The red dots in the upper-left and lower-right corners are our starting and ending points).
The final option labeled "Run (randomized) Kruskal" is what you will eventually need to implement. It turns out we can use the properties of minimum spanning trees to generate a much more interesting (and yet always solvable) maze!
The "Find shortest path" button, once implemented, will draw the shortest path between the two red dots.
Clicking this button should currently throw an exception—we haven't implemented it yet.
If you want to customize the different options (e.g. change the number of rows
and columns in the grid maze, change the percentage of edges removed), look at the
MainWindow.launch
method. Feel free to change any of the constants
there—we will not be looking at this file when grading, so we don't care
what changes you make.
For reference, creating the maze with either of the "Delete random edges" options takes less than half a second on our solution.
Task: complete the ArrayDisjointSet
class.
Notes:
Be sure to use implement your disjoint set using the array-based representation we discussed in lecture. This includes making the optimizations we've discussed, specifically path compression and union-by-rank.
Note that one difference from lecture is that this implementation is generic and so
can store any type. To keep track of the corresponding indices of each value in our
array implementation, you should use an IDictionary<T, Integer>
just
like you did for the ArrayHeap
. This time though, values won't move in the
array, so the dictionary indexing code should be more straightforward than
before.
We have provided a few tests for this class in TestArrayDisjointSet
,
but they're deliberately minimal. We strongly encourage you to add more
tests to make sure your ArrayDisjointSet
is working correctly.
Graph
Task: implement the Graph
constructor and numVertices
and numEdges
methods.
Notes:
You can find this class inside the datastructures.concrete
package.
Your constructor is currently designed to accept a list of vertices and
a list of edges. However, you may find this somewhat inconvenient to work with, especially
once you start implementing the findShortestPathBetween(...)
method. You will
probably want to add extra fields so that you can store the graph
in a more useful representation (e.g. as an adjacency list or adjacency matrix).
While you're working through this problem, there will likely be some design decisions that come up, such as whether to use an adjacency list or matrix, using weighted or unweighted edges, or other small details. If you're confused about what to do here, it might benefit you to read further down in the spec to understand what your graph will represent later on in the project.
This class uses generics in a slightly-more complicated way than you've seen in previous projects. We've tried to insulate you from this as much as possible, but it's possible you may run into unexpected issues or have difficulty getting your code to compile depending on what exactly you're doing.
If this happens to you, please ask for help either on discussion board or during office hours ASAP and we'll help you get unstuck as best as we can. You can also read through past discussion board posts to see if your question has been previously asked.
This is a class about data structures and algorithms, not a class about Java, so we don't want you to waste your time struggling with Java-related issues.
You should make sure to look over the datastructures.IEdge
class.
Any objects of type E
implement the IEdge
methods.
However, be sure not modify this class.
You can find (fairly minimal) tests for this class in
TestGraph
. Again, you'll want to write more tests to
ensure your code matches your intentions.
Graph.findMinimumSpanningTree(...)
Task: implement the Graph.findMinimumSpanningTree(...)
Notes:
You should implement findMinimumSpanningTree(...)
using
Kruskal's algorithm.
You can use top topKSort(...)
to sort your edges.
KruskalMazeCarver
Task: implement the KruskalMazeCarver.returnWallsToRemove(...)
method
If you remember when we were running the maze program from before, the "remove random walls" algorithms ended up generating pretty poor mazes. They either removed too many walls and created trivial mazes, or removed too few and created impossible ones.
What we really want is an algorithm that (a) generates a random-looking maze, (b) makes sure the maze is actually solvable, and (c) removes as few walls as possible.
It turns out that we can use algorithms such as Prim's and Kruskal's to do exactly that!
Here's the trick: we take the maze, treat each room as a vertex and each wall as an edge, assign each wall a random weight, and run any MST-finding algorithm. We then remove any wall that was a part of that MST.
This will end up satisfying all three criteria! By randomizing the wall weights, we remove random walls which satisfies criteria (a). A MST-finding algorithm, by definition, will ensure there exists a path from every vertex (every room) to every other one, satisfying criteria (b). And finally, because MST-finding algorithms try and avoid cycles, we avoid removing unnecessary edges and end up with a maze where there really is only one solution, satisfying criteria (c).
Your task here is to implement this algorithm within the KruskalMazeCarver
class.
Other notes:
You can find this class inside the mazes.generators.maze
package.
Make sure you understand how to use the Maze
and
Wall
objects. The Wall
object is a subclass of
IEdge
, which means you should be able to pass a list or set
of Wall
s into your Graph constructor (along with the corresponding
list of Room
s).
You may import and use java.util.Random
while implementing this
class.
If you're stuck, try taking a look at RandomMazeCarver
, which is
located within the same package. Your algorithm will be a little more complicated,
but it may serve as a good source of inspiration.
To test your method, try running the program and generate a few mazes after selecting the "Run (randomized) Kruskal" option. On our solution, running this option takes a little more than 1 second.
Graph.findShortestPathBetween(...)
Task: implement the Graph.findShortestPathBetween(...)
method
Finally, you will implement the code to actually solve the mazes.
Notes:
You should implement findShortestPathBetween(...)
using
Dijkstra's algorithm.
To represent infinity, use the Double.POSITIVE_INFINITY
constant.
While we definitely encourage you to look at the pseudocode provided in lecture, please be sure to take it with a grain of salt.
We've tried to strike a good balance between the high-level overview and the implementation details, but that means we may have omitted a some details. The pseudocode is meant to be a guide, not an instructional manual, so include other details as you see fit.
In addition, you may find it convenient to arrange your code slightly differently from the way the pseudocode is presented, especially since you're trying to solve a slightly different problem than the one from the lecture slides: the algorithm in lecture finds the shortest paths from the starting vertex to every other vertex, whereas you only need the shortest path to a specific destination vertex.
This doesn't mean you'll be completely rewriting Dijkstra's, but you should be aware that you might need to change things around to better fit your own needs, much like with the pseudocode provided for PageRank in the previous project.
Rather than inserting your vertices directly into your heap, you will want to create and insert objects of a custom inner class instead. Why do you suppose that is?
Recall that IPriorityQueue
requires its contents to implement the
Comparable
interface
and therefore have a compareTo
method, whereas the Graph's generic type V
does not require vertices to be comparable. This means you will need to create a
custom vertex class to store the data of a vertex while also implementing
compareTo
to use in the IPriorityQueue
.
Tips for your custom vertex class:
private static class ExampleComparableVertex<V, E>
implements Comparable<ExampleComparableVertex<V, E>> {
// Add any fields you think will be useful
public ExampleComparableVertex(/* your constructor arguments */) {
// Initialize the object
}
public int compareTo() {
// Define compareTo to determine how your vertices will
// be ordered in the IPriorityQueue
}
}
final
so that they cannot be
mutated. Mutating objects while they are contained in other data structures is
an easy way to create strange bugs.equals
and
hashCode
from java.lang.Object
by not defining
overriding methods for them in your class. The default implementations are
sufficient, and incorrect implementations may cause your objects to misbehave
in dictionaries and sets.Dijkstra's algorithm involves updating the costs of vertices in the heap, but
our IPriorityQueue
interface does not have an
updatePriority
or decreaseKey
method as shown in our
lecture slides. Instead, we can use the replace(oldValue, newValue)
method. This affects how we will use our custom vertex class:
replace
requires that the
newValue
is not already in the queue.If you want to review examples of using the replace
method,
check out this test code from homework 5. Your custom vertex class will probably work somewhat
like the IntWrapper
.
Once you're done and all your tests are passing, try re-running the program and click the "Find shortest path" button. If everything went well, the program should now draw a red line connecting the start and the end! (Or, if there is no valid path, display an alert box stating so.)
Efficient code should be able to generate and solve mazes (or recognize that they are unsolvable) on the default parameters for each maze shape and generator in under 1 second.
Task: Submit responses to the Canvas survey.
Each group member should answer and submit these questions independently on the form on Canvas. As a general rule of thumb, a good survey should take around 5 minutes to complete, but feel free to include as much detail as you want. Points will only be deducted for very short answers.
The following deliverables are due on Friday, June 7 at 11:59pm.
Be sure to double-check and make sure that...
ArrayDisjointSet
class is fully implemented and passes all tests.Graph
class is fully implemented and passes all tests.KruskalMazeCarver
class is fully implemented.Submit by pushing your code to GitLab. If you intend to submit late, fill out this late submission form when you submit.