CSE 403, Spring 2009
Assignment: Status Reports
Due: Sundays by 11:59pm
Turnin: Email to cse403-ta@cs... (Subject [CSE403 Status])
To keep the executives, the customers, and yourselves informed about your
progress, CSRocks is asking you to send them a brief status update each
week. The status update should have three sections, each typically one
paragraph long:
-
The first paragraph is easy—it should be an exact copy of the third
paragraph from last week (i.e. your goals from a week ago).
-
The second paragraph should tell us about the progress you've made this
week: what you've done, what worked, where you had trouble, and what you've
learned.
-
The third paragraph should outline your plans and goals for the following
week (including who is responsible). If tasks from one week aren't yet
complete, they should roll over into your tasks for the next week. It's
good to include some less-detailed longer-range schedule items in this list
as well.
Please email the report, along with your team name, to
cse403-ta@cs..., using the subject line [CSE403 Status] to
make it easy to filter these to a separate location. The status reports
should be submitted by 11:59 PM each Sunday until the completion of the
project.